Cemetry - Bakerton

Started 3rd February — Completed 12th March

Project Scope

  • Marking out on site.
  • Clearing and excavations.
  • Compaction to engineers' specifications.
  • Precast bases & columns.
  • Precast panels.

Execution Details

400m done including all civils, casting and installation in just 5 weeks from date of PO.

  • 5 days to install all bases and columns on site.
  • 4 days to install all the high-level security walling panels.